Published by the Town of Pine Knoll Shores in the Interest of its Citizens Town Hall 247-4353 January 1999 and Rescue 911 PONT FORGET! January 5 is the last day TO PAY 1998 PROPERTY TAXES WITHOUT A PENALTY. Flooding-Eastern Section of Town l^avid Criser, Engineer with Criser & Troutman Consulting Engineers of Wilmington, North Carolina reported on the flooding project estimated schedule for completion. The estimated schedule is as follows: Complete Survey Complete Design Town Review Permitting Bidding Award Contracts Construction December, 1998 January, 1999 February, 1999 May, 1999 June, 1999 July, 1999 November, 1999 Resolutions “Fhe Board of Commissioners approved three Resolutions. One for ■ Hurricane Emergencies. Also, two others that apply to obtaining grants, the first being the replacement of the deteriorated unclaimed bulkhead at McNeil Inlet and the other to procure funds to dredge the two channels at Brock Basin and McNeil Inlet into Bogue Sound.